Steelmaker List of Production Limit and Stoppage in Luanzhou, Tangshan City

https://en.steelhome.com [SteelHome] 2019-06-26 14:37:55

share to social network site

According to Notice of Production Limit and Stoppage of Tangshan Steelmakers issued by Tangshan Government, Luanzhou lists its own steelmakers list of production limit and stoppage.

No.

Mill

Schedule

BF

Sintering Machine

Shaft Furnace (Pellet)

Converter

Lime Kiln

No.& Size (m3)

Shutdown Time

Corpora-tion

No.& Size (m2)

Shutdown Time

Corpora-tion

No.& Size (m2)

Shutdown Time

Corpora-tion

No.& Size (t)

Shutdown Time

Corpora-tion

No.& Size (t/day)

Shutdown Time

Corpora-tion

1

Tangshan Jinma Steel

3# (500)

00:00 June 24-24:00 July 31

50.03%

3# (180)

00:00 June 24-24:00 July 15

50%

12

00:00-12:00 during 24 June-31 July

50%

1#(120)

/

50%

700

12:00-24:00 during 24 June-31 July

50%

1# (1080)

/

2# (1350)

00:00 June 24-00:00 June 31; 22:00 July 12-24:00 July 31

4# (180)

00:00 July 16-24:00 July 31

2# (120)

00:00 June 24-24:00 July 31

2

Tangshan Xinglong Steel

(1080) 1#

00:00 June 27-21:00 July 2528.84days

50%

(112 ) 3#

12:00 July 16-24:00 July 31 (15.5 days)

50%

12

00:00 June 24-24:00 June 30 (7 days)

50%

(50) 1#

Regular production

50%

1-6# (180m3)

00:00 June 24-24:00 July 31 (38  days)

50%

3# (530)

Regular production

4#   (112)

00:00 June 24-12:00 July 16 (22.5 days

00:00 July 20-24:00 July 21 (12 days)

3#  (50)

00:00 June 24-24:00 July 31 (38 days)

3

Tangshan Donghai Steel

1# (1080)

June 27-July 31

50.33%

1# (98)

June 24-July 31

50.33%

1# (12)

June 27-July 23

50%

1# (120)

July 14-July 22

50%

1#-8#

1#6#7#8#   June 27-July 31

50%

2# (1080)

Regular production

2# (112)

July 29-July 31

2# (12)

June 24-July 4

2# (120)

July 23-July 31

1#-8#

2#3#4#5#regular production

3# (450)

June 27-July 31

3# (210)

June 24-July 31

 

 

3# (120)

June 24-July 31

1#

June 27-July 31

4# (600)

July 9-July 31

4# (210)

Regular production

 

 

 

 

2#

Regular production

5# (680)

Regular production

 

 

 

 

 

 

 

 

4

Hebei Donghai Special Steel

1#  (1080)

 

50.42%

1#  (180)

June 24-July 31

50.32%

1# (12)

 

50%

1#(120)

June 24-July 31

50.18%

1-8# (350)

June 24-July 31

50.11%

2#  (1080)

June 24-June 29

2#  (180)

June 24-July 31

2# (12)

June 24-July 31

2# ( 120)

 

9#(350)

June 24-July 10

3# (1080)

 

3# (180)

 

3# (12)

June 24-July 12

3# (120)

June 24-July 31

10—13# (350)

 

4# (1350)

June 24-July 31

4# (180)

June 24-July 15

 

 

4# (120)

June 24-June 26

14-16# (450)

 

5# (1350)

June 24-July 31

5# (200)

June 24-July 31

 

 

5# (130)

 

 

 

6# (1350)

June 24-July 31

6# (200)

 

 

 

6# (120)

June 24-July 31

 

 

7# (1080)

 

7# (200)

 

 

 

 

 

 

 

Related Link:

Tangshan Set Production Limit and Stoppage Schedule for Steel Mills

Steelmaker List of Production Limit and Stoppage in Fengnan District, Tangshan City


(To contact the reporter on this story: molly.shi@steelhome.cn or 86-21-50585358)