According to Notice of
Production Limit and Stoppage of Tangshan Steelmakers issued by Tangshan
Government, Jinxi Steel Group as the only steelmaker in Qianxi County,
sintering machines, blast furnaces, converters and lime kilns are asked
to cut more than 50%.
Sintering Machine |
No. |
Size (m2) |
Capacity (00,000 tonnes) |
Volume of production cut (00,000 tonnes) |
Time |
1# |
195 |
0.5616 |
1.6848 |
July 7-9 |
2# |
265 |
0.7632 |
1.5264 |
July 3-4 |
3# |
210 |
0.6048 |
22.68 |
June 24-July 31 |
4# |
265 |
0.7632 |
1.5264 |
July 18-19 |
5# |
210 |
0.6048 |
22.68 |
June 24-July 31 |
6# |
210 |
0.6048 |
22.68 |
June 24-July 31 |
7# |
265 |
0.7632 |
14.8824 |
July 12-31 |
Total |
|
4.6656 |
87.66 (87.48 shall be cut) |
|
Pellet |
No. |
Size (m2) |
Capacity (00,000 tonnes) |
Volume of production cut (00,000 tonnes) |
Time |
3# |
10 |
0.1369 |
|
|
4# |
10 |
0.1369 |
|
|
5# |
10 |
0.1369 |
5.13375 |
June 24-July 31 |
6# |
10 |
0.1369 |
2.6011 |
July 13-31 |
7# |
10 |
0.1369 |
5.13375 |
June 24-July 31 |
Total |
|
|
12.8686 (12.83438 shall be cut) |
|
BF |
No. |
Size (m3) |
Capacity (00,000 tonnes) |
Volume of production cut (00,000 tonnes) |
Time |
1# |
550 |
0.1644 |
5.754 |
June 27-July 31 |
2# |
550 |
0.1644 |
|
|
3# |
550 |
0.1644 |
5.754 |
June 27-July 31 |
4# |
550 |
0.1644 |
5.754 |
June 27-July 31 |
5# |
550 |
0.1644 |
|
|
6# |
550 |
0.1644 |
|
|
7# |
1280 |
0.2959 |
4.7344 |
July 16-31 |
8# |
1280 |
0.2959 |
|
|
9# |
1280 |
0.2959 |
10.3565 |
June 27-July 31 |
10# |
550 |
0.1644 |
5.754 |
June 27-July 31 |
11# |
550 |
0.1644 |
5.754 |
June 27-July 31 |
12# |
1280 |
0.2959 |
|
|
Total |
|
|
43.8609 (43.729 shall be cut) |
|
Converter |
No. |
Size (t) |
Capacity (00,000 tonnes) |
Volume of production cut (00,000 tonnes) |
Time |
1# |
50 |
0.1897 |
6.639 |
June 27-July 31 |
2# |
50 |
0.1897 |
3.69915 |
July 13-31 |
3# |
50 |
0.1897 |
7.11375 |
June 24-July 31 |
4# |
50 |
0.1897 |
7.11375 |
June 24-July 31 |
5# |
100 |
0.274 |
|
|
6# |
100 |
0.274 |
|
|
7# |
50 |
0.1897 |
3.794 |
June 24-July 31 |
8# |
50 |
0.1897 |
3.33197 |
July 13-31 |
Total |
|
|
31.67935 (31.61625 shall be cut) |
|
Lime Kiln |
|
|
|
|
No. |
Size (m2) |
Capacity (00,000 tonnes) |
Volume of production cut (00,000 tonnes) |
Time |
1# |
|
|
|
|
2# |
|
|
|
|
3# |
|
|
|
June 24-July 31 |
4# |
|
|
|
June 24-July 31 |
5# |
|
|
|
June 24-July 31 |
6# |
|
|
|
June 24-July 31 |
7# |
|
|
|
June 24-July 31 |
8# |
|
|
|
|
9# |
|
|
|
|
10# |
|
|
|
|
11# |
|
|
|
|
12# |
|
|
|
|
Related Links:
Tangshan Set Production Limit and
Stoppage Schedule for Steel Mills
Steelmaker List of Production Limit
and Stoppage in Fengnan District, Tangshan City
Steelmaker List of Production Limit
and Stoppage in Luanzhou, Tangshan City
Steelmaker List of Production Limit
and Stoppage in Guye District, Tangshan City |
(To contact the reporter on this story: molly.shi@steelhome.cn or 86-21-50585358) |