Construction Project Info |
Company Name |
Construction Site |
Equipment |
Capacity after conversion (ten thousand tons) |
Proposed Starting Time |
Proposed Production Time |
Replacement Proportion |
Hebei Tangyin Steel |
Caofeidian District, Tangshan City |
2*1500m3 blast furnaces |
266 |
March, 2019 |
December, 2020 |
1.25:1 |
2*100t converters |
230 |
Exit from Construction Project Info |
No. |
Province(District, City) |
Company Name |
Equipment |
Capacity after conversion(ten thousand tons) |
Time of starting the dismantling |
Time of finishing the dismantling |
Note |
1 |
Tangshan City, Hebei Province |
Hebei Tangyin Steel |
1*2#550m3 blast furnace |
65 |
Before production (December, 2020) |
|
2 |
1*3#1080 blast furnace |
104 |
|
3 |
1*4#750 blast furnace |
80 |
|
4 |
Tangshan Steel |
1*2#2000m3 blast furnace |
84 |
The total capacity is 1.7 million tons, including 670,000 tons
from tangshan steel, 170,000 tons from Tangshan Stainless Steel
and 840,000 tons from Tangyin Steel. The remaining 20,000 tons
will be allocated by HBIS Group. |
5 |
Hebei Tangyin Steel |
2*1#2#120t converters |
270 |
|
|
6 |
Tangshan Stainless Steel |
1*1#80t converter |
6 |
Before production |
The total capacity is 1 million tons, including 940,000 tons
from Tangshan Stainless Steel and 60,000 tons from Tangyin
Steel. |
7 |
Tangshan Steel |
1*2#55t converter |
11.5 |
Already removed |
The total production capacity is 805,000 tons, of which 370,000
tons have been net reduced. Tanggang moves 270,000 tons and
tangyin moves 115,000 tons; The remaining 50,000 tons will be
allocated by he steel group. |
Total |
|
|
|
Steelmaking capacity: 287.5
Ironmaking capacity: 333 |
|
|
|
(To contact the reporter on this story: leo.ji@steelhome.cn or 86-555-2238932) |