According to Guiding Opinion of the State Council on Resolving Severe
Overcapacity, details of capacity replacement plan in Linyi Steel
Investment Group Steel are as below:
Construction Project Info |
Company Name |
Construction Site |
Equipment |
Capacity Conversion (ten thousand tons) |
Proposed Starting Time |
Proposed Production Time |
Replacement Proportion |
Linyi Steel Investment Group Co., Ltd |
Linyi Lingang Economic Development Park |
1*2770m3 BF;
2*120t converters |
Iron making: 231;
Steelmaking: 270 |
2019 |
2021 |
Reduction replacement |
Linyi Steel Investment Group Co., Ltd |
Linyi Lingang Economic Development Park |
90t electric furnace |
Steelmaking: 70 |
2019 |
2020 |
Reduction replacement |
Exit from Construction Project Info |
No. |
Province(District, City) |
Company Name |
Equipment |
Capacity Conversion (ten thousand tons) |
Time to start the dismantling |
Time of finishing the dismantling |
Note |
1 |
Shandong Province |
Linyi Jiangxin Steel |
2*1260m3 BFs; 2*120t converters |
ron making: 232;
Steelmaking: 270 |
Before projects above are finished |
Before projects above are finished |
10,000 tons Iron making capacity and 3,000 tons steelmaking
capacity remained is for reduction replacement and 17,000
tons steelmaking capacity is used for reserved capacity for
2.4 million tons high-end stainless steel project
|
2 |
Shandong Province |
Yantai Development Park Huada Steel |
2*50t electric furnace |
Steelmaking: 72 |
Before projects above are finished |
Before projects above are finished |
|