SteelHome Summary: Steel Mill Maintenance (30 May-6 June 2019)

https://en.steelhome.com [SteelHome] 2019-06-10 09:39:28

share to social network site

Region

Steelmaker

Time

Equipment

Affected Products

Affected Quantity (10,000 tons)

Note

North China

Jinxi Steel

1 Dec. – 1 Jun.

One bars production line

Rebar

0.3/day

Resume production 

1 June (12 days and 18 days)

Large size H-beam production line and medium size H-beam production line

H-beam

15

 

North China

Puyang Steel

17 December 2018

1*800m3 BF

Hot metal

0.3/day

 

North China

Tangshan Ruifeng

6 May

1*450m3 BF

Hot metal

0.15/day

 

7 May

1*680m3 BF

Hot metal

0.23/day

 

North China

Tangshan Chunxing

6 May

1*1080m3 BF

Hot metal

0.32/day

 

North China

Tangshan Donghua

6 May

2*680m3 BFs

Hot metal

0.48/day

 

North China

Tangshan Kaiheng

6 May

1*1080m3 BF

Hot metal

0.32/day

 

North China

Tangshan Guoyi

3 May

1*680m3 BF

Hot metal

0.21/day

 

North China

Tangshan Guoyi

3 May

1*1080m3 BF

Hot metal

0.3/day

 

North China

Tangshan Delong

19 May

1*1080m3 BF

Hot metal

0.3/day

 

North China

Jinding Steel

5 March (4 days)

1*1080mBF

Hot metal

0.86/day

 

North China

Shougang Jingtang

23 April (2 months)

5500mBF

Hot metal

1.1/day

 

North China

Xintai Steel

1-16 June 2019

H-beam production line

H-beam

0.35/day

 

North China

Tiantie

Early June

1750mm HR coil/plate production line

HR coil/plate

0.6/day

 

North China

Shougang Qianan

25 June (40 days)

1*2650mBF

Hot metal

0.65/day

 

North China

Shougang Qianan

25 June (12 days)

1*2250mm hot rolling production line

HR coil/plate

0.9/day

 

North China

Cangzhou CREC

 11 June (14 days)

1*180t converter

1780mm HRC production line

HR coil/plate

11

 

Northeast China

Beitai Steel

1 June

One wire rod production line

Wire rod

5

 

6 May

1# 2850mBF

Hot metal

0.6-0.7/day

 

Northeast China

Jilin Steel

Early December 2018

4*70t electrical furnaces

Rebar and coiled rebar

0.2/day

 

Northeast China

Benxi Steel

26 April-11 June

Steel bar production line

Quality steel

7.5-8

 

Northeast China

Benxi Steel

Early June (20 days)

Galvanizing production line

Galvanized sheet

3

 

Northeast China

Anshan Baode

Early June (20 Days)

Section steel production line

Section steel

10

 

East China

Zenith Steel

20 March85 days

1*1580m3 BF

Hot metal

34

 

East China

Zenith Steel

9 April (15 days)

Two rebar production lines

rebar

10

 

East China

Zenith Steel

12 May (20 days)

One small size

Quality & Special Steel

3

Resume production 

East China

Eastern Special Steel

17 May (15 days)

Small bar production line

20-50mm small bar

2-2.5

 Resume production

East China

Ningbo Steel

12-27 June 2019

1780mm HR production line

HRC

19.5

 

East China

Wuhu Xinxing Ductile Pipes

10-15 June 2019

Quality wire production line

Quality wire

1.2

 

East China

Changjiang Steel

Mid-June (10 days)

Rolled steel

Bar steel

2.5

 

East China

Fangda Special Steel

30 May -19 June 2019

2# 1050m3 BF

Hot metal

0.35/day

 

East China

Ansteel CR Plate (Putian)

15 April

Rolling, continuous annealing and galvanizing production line

Rolled plate, common CRC and galvanized sheet

2.6; 1.98; 0.6;

 

East China

Huanghe Special Steel

1-16 June

One section steel production line

Section steel

1.05

 

East China

Weifang Special Steel

16 May 2019 (15 Days)

One quality wire production line

5.5-20mm wire rod

2.5

Resume production 

East China

Weifang Special Steel

20 June (20 days)

Quality bar production line

Round steel

7

 

East China

Sanming Steel Minguang

27 May ( 22 days)

1*420m3 BF

Hot metal

0.13/day

 

East China

Fujian Sanming Steel

3-7 June

One bar production line

Bar steel

1

 

East China

Shandong chuanyang Steel

1 June (15 days)

Section steel production line

4#-8# angle steel

0.45/day

 

East China

Changzhou Eastern Special Steel

Middle May

Two steel bar production lines

Steel bar

3-4

 

Central South China

Wuyang Steel

16 May (15 days)

4200mm medium plate mill

Medium plate

0.4/day

 

Central South China

Lianyuan Steel

Early and middle June (10 days)

cold rolling production line

CRC

5

 

Central South China

Lianyuan Steel

Early and middle June (5 days)

1*120t converter

rebar

5

 

Central South China

Shaoguan Steel

26 May (6 days)

No. 2 bar production line

rebar

0.2/day

Resume production line 

Central South China

Anyang Steel

9 June

Cold rolling annealing unit

CRC

0.2-0.25/day

 

Central South China

Anyang Steel

31 May (15 Days)

One cold rolling pickling production line

Pickling product

0.4/day

 

Central South China

Liuzhou Steel

1 June

High speed wire rod production line

High speed wire rod

0.3/day

 

Southwest China

Chongqing Steel

1-16 June 2019

One bar production line

Steel bar

2.6

 

Southwest China

Panzhihua Steel

30 May-2 June 2019

One bar production line

Steel bar

0.15/day

Resume production line 


(To contact the reporter on this story: molly.shi@steelhome.cn or 86-21-50585358)