HIGHLIGHTS
West
wall cutback advanced to deliver ore from main ore zone.
Mining
back in main ore zone, improved head grade resulting in significant
increase in concentrate production.
Pellet
production increased for the quarter to 550kt compared with 402kt for the
June 2019 quarter.
Pellet
sales increased for the quarter to 550kt compared with 327kt for the June
2019 quarter.
Decrease
in average received prices for the quarter to US$103.06/t (A$150.04/t)
(FOB Port Latta) compared with US$124.04/t (A$176.62/t) for the June 2019
quarter.
Unit
cash operating cost decreased for the quarter to A$106.36/t compared with
A$162.03/t for the June 2019 quarter. This was due to an increase in
concentrate production to 564kt from 373kt for the last quarter.
Cash
and liquid investments of A$156.08 million and trade receivables of A$0.27
million compared with cash and liquid investments of A$149.63 million and
trade receivables of A$24.88 million for the June 2019 quarter. There has
a been a significant decrease in net trade receivables due to provisional
invoice price adjustments to reflect lower iron ore benchmark prices.
Significant
outlays of approximately A$22.61 million has been made in the quarter on
capital projects including progression of the exploration decline in North
Pit, Caterpillar 789c truck fleet rebuilds and purchase of an EX3600
Excavator. In addition, a 2019 interim dividend payment of A$11.57 million
has been made.
Exploration
Decline 788-metres in and progressing well.
Preparation
works and design continues on the project to improve air flow in the
furnaces.
“Production
has improved during the quarter and we are on plan to achieve the
full-year production forecast.” said CEO Mr. Honglin Zhao.
“Achieved
sales price saw a significant decrease in the quarter due to softening
steel prices and continued uncertainties over the outlook of the global
economy.”
“The
underground feasibility study continues to progress well, with the
Exploration Decline development being carried out on schedule.”
SAVAGE RIVER OPERATIONS
PRODUCTION
|
September Quarter
|
June Quarter
|
March Quarter
|
2019
|
2019
|
2019
|
Total BCM Mined
|
3,523,381
|
3,874,527
|
3,229,189
|
Total Ore BCM
|
445,798
|
423,090
|
468,137
|
Concentrate Produced (t)
|
563,599
|
373,347
|
480,585
|
Weight Recovery (%)
|
40.7
|
26.8
|
39.3
|
Pellets Produced (t)
|
549,681
|
402,344
|
452,640
|
Pellet Stockpile (t)
|
229,159
|
229,920
|
154,192
|
Concentrate Stockpile (t)
|
1,717
|
1,228
|
30,642
|
Operational
activities continue to be managed with a priority focus on safe work. The
business has achieved over 2.5 years Lost Time Injury Free for the
September quarter.
Mining
for the quarter was focused on continued development of the west wall
cutback, and delivering HG ore from the lower benches in North Pit. The
west wall cutback was advanced to a position to allow access to the Main
Ore Zone. Consequently, head grade was significantly increased, which can
be seen in increased concentrate and pellet production for the quarter.
Initial
access to the main ore zone did not provide an optimal blend of ore types,
but that improved throughout Q3 and production is on track to deliver at
full rates in Q4.
SHIPPING AND SALES
|
September Quarter 2019
|
June Quarter 2019
|
March Quarter 2019
|
Iron Ore Pellet Sales (dmt)
|
550,442
|
326,616
|
487,799
|
Iron Ore Concentrate Sales (dmt)
|
0
|
45
|
36
|
Iron Ore Chip Sales (dmt)
|
20,148
|
19,465
|
20,658
|
TOTAL Iron Ore Product Sales (dmt)
|
570,590
|
346,126
|
508,493
|
Average Realised Product Price
(US$/t FOB Port Latta)
|
103.06
|
124.04
|
117
|
Average Realised Exchange Rate (AUD:USD)
|
0.6869
|
0.7023
|
0.7129
|
Average Realised Product Price
(A$/t FOB Port Latta)
|
150.04
|
176.62
|
164.12
|
The
average price received during the quarter of US$103.06/t (A$150.04/t) (FOB
Port Latta), decreased by 16.91% from US$124.04/t (A$176.62/t) for the
June 2019 Quarter.
MINE DEVELOPMENT PROJECTS
North Pit Underground
Geological
modelling continued in Q3. Phase 2 drilling to test resource extensions
for the North Pit Underground project were completed and the Phase 3
drilling program from the exploration decline commenced. Updates to
interpretation of the resource model was progressed.
The
Exploration Decline is progressing to plan, with the face position in 788m
as at the end of September. The Phase 3 drilling program is progressing
well with 4 holes completed for an advance of 2,247 metres. These diamond
holes are being drilled directly from the Exploration Decline through the
fault zone and into the main ore zone to provide detailed geotechnical
information and improve confidence in the orebody at depth. A second rig
will be mobilized to site in Q4 to accelerate the drilling activity.
Centre Pit
The
feasibility study for Centre Pit was progressed in Q3 and will be
finalised early in Q4. Geotechnical slope analysis and modelling was
completed and operational planning undertaken to allow commencement of the
first stage of operation. Environmental approval process was undertaken
through the quarter.
Port Latta Improvement Projects
Work
continues to rebuild the fifth furnace. This involved demolition works of
redundant infrastructure around the furnace in preparation for the
rebuilding and modification to the design. This has not been utilised in
the current operation, and engineering design work is in progress to
modify the furnace to improve the flow of air through the pellets. If
successful, this will improve pellet quality and reduce energy
consumption. Once the design work is complete, it is expected the
modifications will be undertaken in 2020.
SOUTHDOWN MAGNETITE PROJECT
(Grange
70%, SRT Australia Pty Ltd 30%)
The
process of seeking a strategic investor(s) for the project is ongoing.
All
tenements, permits and project assets continue to be maintained in good
order. Budgeting and cost control over expenditure on this project
continues to secure the investment.
The
Joint Venture Partners continue to monitor all ongoing project
requirements. This is to ensure that the current status of the feasibility
studies allow the full recommencement of the project once the Joint
Venture is able to secure an equity partner for a strategic share of the
Company’s interest in the project.
Related Link: Official Document
|