Performance
Gross profit in the
third quarter from our steelmaking coal business unit was $425 million
compared with $634 million a year ago. Gross profit before depreciation
and amortization in the third quarter declined by $182 million from a year
ago (see table below), primarily due to a 9% decrease in steelmaking coal
prices and a 9% decline in sales volumes. These items were partially
offset by higher royalties received in respect of our Greenhills
Operations under the joint venture extension agreement signed in the first
quarter of 2019.
Third quarter sales
volumes of 6.1 million tonnes were 9% lower than a year ago and below our
guidance range of 6.3 to 6.5 million tonnes. In the quarter, our sales
were affected by material handling issues and planned construction outages
as the facility upgrade at Neptune Bulk Terminals progressed, which
limited our ability to overcome the shortfall. Efforts are focused on
resolving the material handling issues. Our third quarter sales could have
exceeded the high end of our guidance range had there been no logistical
issues.
The table below
summarizes the change in gross profit, before depreciation and
amortization, in our steelmaking coal business unit for the quarter:
STEELMAKING COAL BUSINESS UNIT
(CAD$
in millions)
|
Three
months ended September 30
|
Nine
months ended September 30
|
Year
|
2019
|
2018
|
2019
|
2018
|
Steelmaking
coal price (realized US$/tonne)
|
$156
|
$172
|
$175
|
$186
|
Steelmaking
coal price (realized CAD$/tonne)
|
$206
|
$224
|
$233
|
$240
|
Production
(million tonnes)
|
6.5
|
6.4
|
19
|
18.9
|
Sales
(million tonnes)
|
6.1
|
6.7
|
18.7
|
19.4
|
Gross
profit before depreciation and amortization
|
$628
|
$810
|
$2,456
|
$2,770
|
Gross
profit
|
$425
|
$634
|
$1,871
|
$2,221
|
Property,
plant and equipment expenditures
|
$184
|
$120
|
$481
|
$280
|
Outlook
Consistent
with the guidance issued in the second quarter, we continue to expect our
2019 production to be between 25.5 and 26.0 million tonnes.
We
are expecting sales volumes in the fourth quarter of 2019 to be
approximately 6.2 to 6.4 million tonnes. Planned outages at Ridley
Terminals and Neptune Bulk Terminals will result in approximately 40 lost
train dumping or berthing days, affecting our sales volumes in the fourth
quarter.
In
response to declining coal prices, we have deferred our planned capital
expenditures by an additional $70 million from the previous guidance. We
now expect our 2019 capital expenditures to be $120 million lower than our
original guidance, with some of the reductions due to the timing of
expenditures. Of the $70 million, $60 million relates to sustaining
capital expenditures and $10 million relates to major enhancement capital
expenditures.
As
disclosed in the second quarter, mine sequence changes at some of our
operations have increased our expected capitalized stripping costs in 2019
to approximately $445 million, above our original guidance of $410
million. This is a timing issue and spending on stripping activities in
2019 will reduce stripping costs in future years.
We
continue to progress the Neptune Bulk Terminals facility upgrades, which
will significantly increase terminal-loading capacity and improve our
capability to meet our delivery commitments to our customers while
lowering our overall logistics costs. The definitive cost estimate for the
project is expected to be complete in the fourth quarter. The cost of the
project has risen as a result of various factors including effects of
executing construction activities within an active port operation,
additional project scope, engineering design evolution, difficult
geotechnical conditions and field productivity. Current indications are
that the total cost of the project is expected to be in the range of $750
to $800 million. In light of the supply chain performance issues we have
experienced, including ongoing contamination of our product by
sub-bituminous coal, which adversely affects our customers, the business
case for this project remains strong. It will provide us with an exclusive
terminal that meets the long-term requirements of our customers for
consistent, high-quality product at significantly reduced costs. The
Neptune Bulk Terminals facility upgrades are expected to be completed in
the first quarter of 2021.
Pricing
softened in the third quarter of 2019, reflecting the pressure on
steelmakers’ margins created by lower steel pricing and continued high
iron ore prices. A number of steelmakers reduced production as uncertainty
created by trade disputes and the global economy slowdown persist. While
our cost of sales will be lower in the fourth quarter of 2019, we plan to
complete the majority of our major plant outages earlier in 2020, reducing
our steelmaking coal production in the first half of the year and
increasing production in the third and fourth quarters. As a result, we
expect quarterly cost of sales to be significantly higher in the first
quarter of 2020 than the fourth quarter of 2019 with the lower production
rates, and then decreasing significantly in the second half of the year
when we are back to full production levels. Overall, we expect our cost of
sales to be lower in 2020 than in 2019. As in prior years, annual
production volumes can be adjusted to reflect market demand for our
products, subject to adequate rail and port service. Assuming that current
market conditions persist, annual production in 2020 is expected to be
similar to 2019.
Related
Link: Official
Document
|