Key Points (all currency in
Australian dollars unless stated otherwise):
1.
Iron ore sales of 1.4 million wet metric tonnes (Mwmt) in the
quarter, comprising 0.7 Mwmt of Koolan Island high-grade fines and 0.7
Mwmt of low-grade material from the Mid-West operations.
2.
Group cashflow for the quarter of $32 million.
3.
Cash and liquid investments of $445 million at 30 September 2020
after payment of the $16 million cash component of last financial year’s
dividend, and no borrowings.
4.
Group unit cash costs of $56/wmt Free on Board (FOB) for the
quarter, before Koolan advanced waste stripping investment of $24
million. Koolan site cash costs were $66/wmt FOB before the advanced
waste stripping, and Mid-West cash costs were $40/wmt FOB.
5.
Reported 2019/20 financial year net profit after tax of $84
million, and a fully franked final dividend of 3.0 cents per share
distributed on 24 September 2020.
6.
Ore sales guidance for 2020/21 of 2.8-3.3 Mwmt at a group cash
cost of $60-65/wmt FOB before waste stripping investment at Koolan
Island of approximately $100 million and other Koolan capital
improvement projects of approximately $20 million.
7.
Koolan Island new airstrip certified and commissioned, with first
flights scheduled for October 2020.
8.
Group Mineral Resources of 69.4Mt @ 61.7% Fe and Ore Reserves of
18.7Mt @ 65.2% Fe reported as at 30 June 2020.
9.
Subsequently, Mount Gibson has declared an Ore Reserve estimate
for Stage 1 of the Shine Iron Ore Project in the Mid-West, targeting
first ore sales in mid-2021 for a two year period, with the potential
for a further two year extension thereafter.
Note: Cash costs are reported
FOB and include operating costs, royalties, sustaining capital
expenditure and allocated corporate costs but are before waste stripping
investment and capital improvement projects at Koolan Island.
Comment
Mount Gibson Chief Executive
Officer, Peter Kerr, said: “Mount Gibson has made a positive start to
the new financial year with improved quarterly ore production and sales,
completion of the new Koolan Island airstrip, ongoing low-grade ore
sales in the Mid-West and, recently, declaration of Ore Reserves for the
initial stage of the Shine Project.
“This provides a strong base as
we move into the peak phase of waste stripping at Koolan Island to be
completed in the next 12-18 months. We expect Koolan Island ore sales of
1.8-2.1 Mwmt this financial year, weighted to the latter part of the
June half. Once the stripping phase is completed, we expect
significantly increased ore sales and cashflow at Koolan Island from
early 2022 onwards.
“We are also tracking to achieve
first ore sales from the Shine Project in mid-2021, subject to
finalising the last commercial and permitting requirements, which will
extend our Mid-West business by at least two years and potentially
longer should market conditions remain supportive.”
PERFORMANCE AT A GLANCE
|
|
Sep-19 |
Dec-19 |
Mar-20 |
Jun-20 |
Sep-20 |
2020/21 |
Unit |
Quarter |
Quarter |
Quarter |
Quarter |
Quarter |
Year to Date |
Standard DSO product
sales |
kwmt |
664 |
733 |
439 |
516 |
672 |
672 |
Low-grade sales |
kwmt |
711 |
649 |
587 |
643 |
701 |
701 |
Total Ore Sales |
kwmt |
1,375 |
1,382 |
1,026 |
1,158 |
1,373 |
1,373 |
Platts 62% Fe CFR price,
average |
US$/dmt |
102 |
89 |
89 |
93 |
118 |
118 |
Platts 65% Fe CFR price,
average |
US$/dmt |
110 |
98 |
104 |
108 |
129 |
129 |
Realised Koolan fines
FOB price* |
US$/dmt |
95 |
73 |
86 |
97 |
104 |
104 |
Realised Mid-West fines
FOB price# |
US$/dmt |
29 |
26 |
27 |
28 |
30 |
30 |
Realised Mid-West lump
FOB price# |
US$/dmt |
35 |
35 |
37 |
40 |
41 |
41 |
Minor discrepancies may
occur due to rounding. |
* Realised Koolan FOB
(Free on Board) prices reflect a mix of month of shipping (M),
M+1 and M+2 averages, referencing the Platts 62% and 65% Fe
indices. Realised prices are shown after shipping freight,
provisional pricing adjustments and specification
adjustments/penalties. |
# Realised Mid-West FOB
prices are shown after shipping freight and specification
adjustments/penalties. kwmt = thousand wet metric tonnes. |
US$/dmt = USD per dry
metric tonne. |
For the purpose of wet
to dry tonnage conversion, moisture content typically averages
circa 3% for Koolan Island fines and circa 4% for Mid-West
products. |
OPERATIONS
Sales of high-grade ore from
Koolan Island totalled 0.7 Mwmt in the September quarter. In addition,
0.7 Mwmt of low-grade material from Extension Hill was shipped from the
Geraldton Port in the quarter. Operating statistics are tabulated in
Appendix A.
Koolan Island
A total of 5.2 Mwmt of ore and
waste was mined at Koolan Island during the September quarter, a 35%
increase on the prior quarter. Mining performance improved significantly
following the onset of the dry season, the successful removal of
saturated sediments in the western end of the Main Pit floor, and
generally improved mining productivity as the operation ramps up for the
planned elevated waste mining movement in the upper levels of the pit
over the next 12-18 months.
Ore production in the September
quarter totalled 672,000 wmt compared with 805,000 wmt in the prior
quarter, reflecting the waste movement cycle. Ore sales increased 30% to
672,000 wmt in nine shipments, two more than in the prior quarter. The
average grade of shipments in the quarter was 63.8% Fe, in line with the
mine plan. Sales from Koolan Island are made under long term offtake
agreements on FOB terms, with the sale occurring upon shipment loading
at Koolan Island. At current spot prices for high-grade iron ore and
based on an average product grade achieved in the quarter, each Panamax
cargo has a gross value of approximately $10-11 million FOB.
Geotechnical works on the
island-side Main Pit footwall (i.e. depressurisation drilling, cable
bolting, shotcreting and installation of safety mesh) continue to plan.
Seawall (hanging wall) instrumentation continues to demonstrate that the
seawall, which incorporates the installed impermeable seepage barrier
and has been under full tidal loads since late 2018, is safe and
successfully performing to design expectations.
Koolan Island generated
operating cashflow of $50 million in the quarter before capitalised
waste stripping investment of $24 million, resulting in net site
cashflow of $26 million. Operating costs are detailed in the Cost
Performance section of this report.
As previously indicated, the
planned elevated stripping phase of the mine, during which waste
movement and operating costs are at their highest and ore production is
most variable, is scheduled to be completed over the next 12-18 months.
Thereafter, sales will rise and cash costs will decline in step with the
significantly reduced waste to ore stripping ratio.
Total mining volumes in 2020/21
are targeted to increase by approximately 50% (with a waste to ore
stripping ratio of ~9.4x) compared with the last financial year, and ore
sales will be variable from quarter to quarter while being weighted to
the latter part of the second half of the financial year. Shipments will
be at their lowest in the in the December 2020 and March 2021 quarters
as the waste movement cycle reaches its peak and the wet season impacts
are typically most pronounced. Waste movement will be focused on the
upper levels of the pit during this period, and enhanced by the
commissioning of an additional production excavator and haul trucks.
Unit mining and administration
costs, including all logistics and sustaining capital expenditure, are
targeted to reduce to around $9 per tonne of material (ore or waste)
moved. This target was achieved in the September quarter. Reported site
cash costs per tonne of ore sold will necessarily reflect the elevated
strip ratio and the lower ore production during this waste stripping
phase.
Investment in advanced waste
stripping is anticipated to total circa $100 million for the year, with
approximately $20 million also targeted for other Koolan Island capital
improvement projects. These projects include an upgrade of the existing
crushing plant to ensure it will be capable of processing the
significantly increased ore throughout expected to occur from next
financial year onwards.
Infrastructure Investment -
Airstrip
As previously reported, the
Company has constructed a new 2.1 kilometre sealed all-weather airstrip
in the centre of the Island, on time and under the $20 million budget.
Just after the end of the
quarter, the airstrip was successfully commissioned via a test flight of
a Fokker 100 jet aircraft. The first passenger flight, planned to carry
circa 100 personnel from Perth direct to Koolan Island, is scheduled to
take place in mid-October, with two return services scheduled weekly
thereafter.
This new airstrip is expected to
deliver significant safety, efficiency and cost reduction benefits to
the Koolan Island operation by enabling direct jet flights from Perth,
reducing the average commute time for Perth personnel by approximately
half. The COVID-19 pandemic has further demonstrated the value of this
development.
Mid-West Operations
Mount Gibson commenced the
existing low-grade sales program from the Extension Hill mine site in
June 2019. Sales since that time have now totalled over 3.5 Mwmt.
Sales in the September quarter
were in line with plan totalling 701,000 wmt, comprising 416,000 wmt of
low-grade lump material and 285,000 wmt of low-grade fines.
Cashflow for the quarter from
the Mid-West operations totalled $8 million, including $2 million from
the ongoing rail credit refund.
Operations in the Mid-West
continue to proceed well and costs remain in line with plan (refer Cost
Performance section of this report). Regional travel restrictions to
limit the spread of COVID-19 were lifted in May and have not
significantly impacted the Mid-West operations. Mount Gibson remains
ready to respond promptly in the event of any required reinstatement of
government or other restrictions.
Marketing to further extend the
low-grade sales program to the end of calendar 2020 is ongoing based on
remaining available low grade stockpiles and additional recoverable
low-grade material adjacent to the Extension Hill pit.
As per guidance provided in
August, the Company is targeting total low-grade sales of 1.0-1.2 Mwmt
by the end of calendar 2020. Thereafter the Extension Hill site is
expected to transition to closure.
Total ore sales since Extension
Hill commenced production in late 2011 have to date totalled in excess
of 25 Mwmt, including sales from the Iron Hill deposit and low-grade
material. Extension Hill commenced production with initial ore reserves
of 14.5Mt.
Shine Project
Mount Gibson reactivated
development planning work for the Shine Iron Ore Project in early 2020.
The project, located approximately 85km north of the Extension Hill mine
site, was deferred amid deteriorating market conditions in late 2014 but
remains a near-term production opportunity with minimal start-up capital
requirements.
On 9 October 2020, Mount Gibson
declared Ore Reserves of 2.8Mt grading 59.4%1 Fe in the proposed
“Stage 1” pit at Shine, from
which the Company plans to commence ore sales in mid-2021.
The Company estimates capital
development costs of $17-20 million, with production to average
approximately 1.5Mtpa over an initial two-year period at an average cash
operating cost of $65-70/wmt FOB before royalties.
Should market conditions remain
supportive, there is potential to extend the mine life by a further two
years by proceeding with a “Stage 2” pit, based on measured and
indicated Mineral Resources within the modelled pit shells. The Shine
project has total Measured, Indicated and Inferred Hematite Resources of
10.8Mt grading 58.2% Fe.
The base case assumes ore is
hauled approximately 300km by road from the mine site to the Company’s
established export facilities at Geraldton Port. However, potentially
more cost effective alternative transport options are also under
discussion with third parties.
State environmental approval was
renewed in May 2020 and remaining permitting and commercial requirements
are currently being pursued.
Cost Performance
Group cash costs averaged
$56/wmt FOB in the September quarter (before advanced waste stripping
investment at Koolan Island totalling $24 million), compared with
$72/wmt FOB (and $79/wmt FOB including $7 million of advanced waste
stripping) in the preceding quarter.
At Koolan Island, site cash
costs averaged $66/wmt FOB in the quarter before waste investment of $24
million. Site cash costs will align with waste stripping volumes over
the coming year and then reduce over the life of the mine as sales
volumes increase and the waste/ore strip ratio progressively declines.
In the Mid-West, site cash costs
averaged $40/wmt FOB for the quarter, in line with guidance.
Sales and Cost Guidance for
2020/21
As previously reported, the
focus in 2020/21 will be on increased mining movements at Koolan Island
to substantially complete the planned open pit waste stripping phase
ahead of ore shipment levels rising significantly from the following
year onwards. In the Mid-West, the focus will be on completing low grade
sales from Extension Hill and bringing the Shine project into production
as quickly as possible.
Consequently, Mount Gibson
expects total Group sales of 2.8-3.3 Mwmt at a cash cost of $60-65/wmt
FOB for the current financial year, before approximately $100 million in
advanced waste stripping and $20 million in capital upgrades at Koolan
Island.
Koolan Island is expected to
contribute 1.8-2.1 Mwmt of high grade iron ore fines sales in the year,
with site operating cash costs expected to average $60-65/wmt FOB before
the above-mentioned waste stripping investment and capital upgrade
projects. Sales will be weighted toward the latter part of the financial
year, with lower volumes in the December and March quarters.
In accordance with the Koolan
life-of-mine plan, Mount Gibson originally anticipated that the waste
stripping investment would not result in a positive cashflow for the
2020/21 financial year. However, at prevailing iron ore prices, net
cashflow from Koolan this year could be modestly positive. Following
this waste stripping investment, the operation will see substantial
increases in production, sales and cashflow generation from next
financial year onwards.
The Mid-West operations are
expected to contribute 1.0-1.2 Mwmt at an average cash cost of
$40-45/wmt FOB, comprising the sale of remnant low grade material from
the Extension Hill site.
Guidance does not presently
include any contribution from the Shine Project.
Annual Statement of Mineral
Resources and Ore Reserves
On 23 September 2020, the
Company released its annual statement of Mineral Resources and Ore
Reserves as at 30 June 2020. Group Mineral Resources totalled 69.4
million tonnes (Mt) grading 61.7% Fe and Ore Reserves totalled 18.7Mt at
65.2% Fe. This compared with 74.2Mt at 61.8% Fe and 20.3Mt at 65.5% Fe
respectively in the prior year, reflecting additions from mine design
improvements net of mining depletion at Koolan Island, and the removal
of remnant resources at the now-rehabilitated Tallering Peak mine-site
in the Mid-West.
Quarterly Operating
Statistics
|
Sep-19 |
Dec-19 |
Mar-20 |
Jun-20 |
Sep-20 |
2020/21 |
Quarter |
Quarter |
Quarter |
Quarter |
Quarter |
Year to Date |
KOOLAN ISLAND |
(kwmt) |
(kwmt) |
(kwmt) |
(kwmt) |
(kwmt) |
(kwmt) |
Mining & Crushing |
|
|
|
|
|
|
Waste
mined |
2,985 |
3,276 |
3,113 |
3,053 |
4,544 |
4,544 |
Ore
mined |
651 |
763 |
545 |
805 |
672 |
672 |
Ore
crushed |
661 |
722 |
432 |
556 |
683 |
683 |
Shipping/Sales* |
|
|
|
|
|
|
Standard DSO Lump |
- |
- |
- |
- |
- |
- |
Standard DSO Fines |
664 |
733 |
439 |
516 |
672 |
672 |
Total |
664 |
733 |
439 |
516 |
672 |
672 |
MID-WEST |
|
|
|
|
|
|
Mining & Crushing |
|
|
|
|
|
|
Waste
mined |
- |
- |
- |
- |
- |
- |
Ore
mined |
- |
- |
- |
- |
- |
- |
Low-grade material crushed |
882 |
694 |
484 |
265 |
680 |
680 |
Shipping/Sales* |
|
|
|
|
|
|
Standard DSO Lump |
- |
- |
- |
- |
- |
- |
Standard DSO Fines |
- |
- |
- |
- |
- |
- |
Low-grade Lump |
473 |
478 |
233 |
232 |
416 |
416 |
Low-grade Fines |
238 |
172 |
354 |
410 |
285 |
285 |
Total |
711 |
649 |
587 |
643 |
701 |
701 |
CONSOLIDATED DATA |
|
|
|
|
|
|
Shipping/Sales* |
|
|
|
|
|
|
Standard DSO Lump |
- |
- |
- |
- |
- |
- |
Standard DSO Fines |
664 |
733 |
439 |
516 |
672 |
672 |
Low-grade Lump |
473 |
478 |
233 |
232 |
416 |
416 |
Low-grade Fines |
238 |
172 |
354 |
410 |
285 |
285 |
Total |
1,375 |
1,382 |
1,026 |
1,158 |
1,373 |
1,373 |
(To contact the reporter on this story: cody.wang@steelhome.cn or 86-555-2238837 18725550282) |