Highlights
1.
Safety performance continued to improve, with a 12-month rolling
Lost Time Injury Frequency Rate (LTIFR) of zero and a Total Reportable
Injury Frequency Rate (TRIFR) of 3.19 at September 2020, an improvement
of 3% over the quarter.
2.
COVID-19 Polymerase Chain Reaction (PCR) screening testing
continued with 42,055 tests completed during the quarter and more than
75,000 completed this year through MRL’s 10 screening facilities in
metropolitan Perth and regional areas across Western Australia (WA).
3.
Mining Services volumes increased 24% versus Q120 and 7% versus
Q420, in line with expectations. Guidance remains for FY21 volumes to
increase 20 to 25%.
4.
Total iron ore production remained steady at 4.2 million (m) wet
metric tonnes (wmt) for the quarter.
5.
Koolyanobbing operations shipped 2.2m wmt iron ore for the
quarter with production expected to ramp up to meet full year guidance.
6.
Iron Valley shipped 1.3m wmt iron ore for the quarter, in line
with the mine plan and guidance.
7.
Average iron ore revenue received of US$97 per dry metric tonne
(dmt) during the quarter, 15% higher than the previous quarter.
8.
During the quarter, MRL agreed to purchase the Wonmunna Iron Ore
Project (Wonmunna) from Australian Aboriginal Mining Corporation Limited
(AAMC). The purchase was for an immaterial cash consideration and a
royalty which MRL will pay AAMC in respect of the first 40m dmt
extracted and removed from the area. Wonmunna has a forecast capital
cost of approximately $126m (including the acquisition cost) with an
initial design of 5.0m wmt per annum production. Exports of 1.0m to 2.0m
wmt are expected in H2 FY21. Operating costs are expected to be similar
to MRL’s nearby Iron Valley operation.
Table: Production and Sales Summary
'000 wet metric
tonnes |
3Q2020 |
2Q2020 |
3Q2019 |
PRODUCED |
SHIPPED |
PRODUCED |
SHIPPED |
PRODUCED |
SHIPPED |
Iron Valley |
1,543 |
1,313 |
1,674 |
1,783 |
1,409 |
2,056 |
Koolyanobbing |
2,644 |
2,236 |
2,521 |
2,647 |
1,679 |
1,413 |
TOTAL IRON ORE |
4,187 |
3,549 |
4,195 |
4,430 |
3,088 |
3,469 |
Koolyanobbing
Ore delivery and hydrogeology
issues in the Deception pit caused material handling issues in the
supply chain, which hampered production for the quarter. This required
changes to blending to allow efficient crushing and railing activities
while still maintaining quality.
Mining operational procedures
were amended to compensate for the hydrogeology issues by substituting
low strip ratio material movement in W7. Work in the F1 pit commenced in
earnest during the quarter, with access established in July. Windarling
and Jackson pits remained in steady state with some delays experienced
in August across all pits due to weather impacts.
Crushing operations, hampered in
part by the impacts of Deception material, prompted MRL to introduce a
new Mobile Crushing Plant to supplement the primary Koolyanobbing
crusher in order to meet the required run rate. The new plant was
successfully commissioned in early August.
Shipped tonnes of 2.2Mt in the
quarter were down due to the material handling issues. Production and
shipping are being ramped up in Q2 to Q4 as planned. FY21 guidance
remains unchanged at 12 to 12.7mt with a year-end run rate of 13mtpa.
Iron Valley
At Iron Valley, a successful
dewatering campaign and robust risk management of ground conditions
facilitated the completion of the C8 pit. Focussed effort on waste
movement in Stage 1 and 2 in C10 has exposed the ore body to meet the
shipping schedule in Q2.
Mining and crushing were
supplemented by the recommenced Phils Creek pit, which will provide
lower phosphorus blending options. Shipped tonnes of 1.3Mt in the
quarter were down on Q4 FY20 because of the timing of the final
shipment, which fell into Q2. FY21 Guidance remains unchanged at 7.5 to
8.5mt with a year-end run rate of 9mtpa.
More Info:
Quarterly Exploration and Mining Activities Report July to September
2020 |