Operations
1.
Following the Government's COVID-19 containment directives, on
March 24, 2020, the Company announced that it will ramp down operations
at the Bloom Lake Mine. The Government subsequently issued directives,
effective April 15, 2020, which the Company complied with by gradually
ramping up operations at Bloom Lake, as announced on April 23, 2020, as
mining activities were categorized by the Government as a "priority
service" and allowed to resume normal operations in the province of
Québec;
2.
Quarterly production of 1,798,800 wmt of high-grade 66.5% Fe iron
ore concentrate for the three-month period ended June 30, 2020, compared
to 1,989,400 wmt of high-grade 66.2% Fe iron ore concentrate during the
same prior year period;
3.
Recovery rate of 82.3% for the quarter ended June 30, 2020,
compared to a recovery rate of 82.1% for the same quarter in 2019;
4.
Free On Board ("FOB") Total cash cost1 ("Total Cash Cost" or
"Cash Cost") of $58.4/dmt (US$42.2/dmt) (C1) for the quarter ended June
30, 2020, compared to $54.3/dmt (US$40.6/dmt) for the same quarter in
2019; and
5.
Following the confirmation that its initial commercial production
test qualified as Direct Reduction ("DR") pellet feed material, the
Company produced an additional 207,900 wmt of DR quality iron ore
concentrate at 67.8% Fe with a combined silica and alumina content of
2.68%.
Other Developments
In connection with Bloom Lake's
Phase II expansion project, which proposes to double the mine's
nameplate capacity to 15 Mtpa, the Company resumed some discretionary
capital spending and increased the initial $68M Phase II-related budget
announced on June 20, 2019 by $30M, in order to prudently advance the
project and preserve key timelines ahead of the deferred final Board of
Directors decision to be made at a later date;
Positioned the Company for
additional growth opportunities by increasing its exploration mineral
rights adjacent to the Bloom Lake mining lease by over 175%, following
the acquisition of 152 claims (38 km2), and staking of 127 claims (31.75
km2), directly North of Bloom Lake's operations;
Entered into a freight contract
for one vessel per month until December 2020 at an agreed upon price of
US$15.46 per tonne plus freight commissions; and
Completed the Company's first
Sustainability Report, highlighting an alignment with stakeholders
regarding diligence on corporate and social governance responsibilities,
and which is available on the Company's website at www.championiron.com.
"Today's results continue to
highlight our team's agility in adapting operations while upholding our
Company's core values. Despite temporarily ramping down operations early
in the quarter, as per the Government's COVID-19 containment directives,
our Company delivered record profitability while implementing strict
measures to mitigate the risks of the COVID-19. Additionally, the
production and shipment of additional DR quality iron ore concentrate,
coupled with the substantial increase in mineral rights ownership
adjacent to our operations and our diligence in managing the pandemic
further positions our Company as a leader in the industry. With Bloom
Lake's operations returning to normal levels, our focus remains on the
health and safety of our employees, partners and communities", commented
David Cataford, Champion's CEO.
BLOOM LAKE MINE OPERATING
ACTIVITIES
|
2020 Q2 |
2019 Q2 |
Operating Data |
|
|
Waste
mined (wmt) |
2,612,800 |
3,580,900 |
Ore
mined (wmt) |
4,682,600 |
5,105,100 |
Material mined (wmt) |
7,295,400 |
8,686,000 |
Strip
ratio |
0.6 |
0.7 |
Ore
milled (wmt) |
4,604,600 |
4,780,000 |
Head
grade Fe (%) |
31.3 |
32.5 |
Recovery (%) |
82.3 |
82.1 |
Product Fe (%) |
66.5 |
66.2 |
Iron ore concentrate produced (wmt) |
1,798,800 |
1,989,400 |
Iron ore concentrate sold (dmt) |
1,758,800 |
1,906,700 |
Financial Data (in thousands of dollars) |
|
|
Revenues |
244,574 |
277,914 |
Cost
of sales |
102,776 |
103,607 |
Cost
of sales - incremental costs related to COVID-19 |
4,562 |
— |
Other
expenses |
9,541 |
7,371 |
Net
finance (income) costs |
-1,322 |
29,052 |
Net
income |
75,556 |
74,241 |
EBITDA |
127,695 |
166,936 |
Statistics (in dollars per dmt sold) |
|
|
Average realized selling price |
139.1 |
145.7 |
Total
cash cost (C1 cash cost) |
58.4 |
54.3 |
All-in
sustaining cost |
64.8 |
62.8 |
Cash
operating margin |
74.3 |
82.9 |
Operational Performance
On March 24, 2020, the Company
announced the ramp down of its operations following directives from the
Government in response to the COVID-19 pandemic, which required mining
activities to be reduced to a minimum within the province. The
operations progressively resumed as announced by the Company on April
23, 2020, following the announcement from the Government that mining
activities were to be considered a "priority service". Although the
Company was operating at a minimal capacity for a period of time and its
activities at the mine were disrupted, early actions implemented by
management in response to the COVID-19 pandemic have minimized its
impacts on operations. This has allowed production to reach nearly 1.8
million wmt, which is in line with the plant nameplate capacity and
represent only a 10% reduction, when compared to the same quarter of the
previous fiscal year.
The quarterly production was
also impacted by a scheduled semi-annual shutdown. As a result of the
COVID-19 new measures and related inefficiencies, the shutdown scope was
reduced and additional days were required. A small portion of the work
initially planned for this scheduled shutdown was not completed, with
the remainder of the required work postponed and expected to be
completed later in the year. The second planned shutdown is scheduled
for the third quarter of Champion's fiscal year ending March 31, 2021.
During the three-month period
ended June 30, 2020, 7,295,400 tonnes of material were mined, compared
to 8,686,000 tonnes in the same period of the prior year, representing a
decrease of 16%. This reduction is attributable to the negative impact
of the COVID-19 pandemic on several of the Company's activities
including: a reduced mining activity level due to compliance with the
public health directives issued by the Government; reduced equipment
maintenance due to COVID-19-related resources limitations, which had
adverse repercussions on equipment availability; and the arrival of the
seasonal workforce, which required integration and training.
The plant processed 4,604,600
tonnes of ore during the first quarter of the fiscal year 2021, compared
to 4,780,000 tonnes in the comparable prior year period, representing a
decrease of 4%. The variation is a direct result of the COVID-19 imposed
ramp-down, as only one of the Company's two production lines remained in
operation for a period of time.
The Company achieved an average
recovery rate of 82.3% during the first quarter of the fiscal year 2021,
compared to a recovery rate of 82.1% in the same period of the prior
year, which remained relatively stable. Several factors adversely
impacted the recovery rate during the quarter, such as the ramp down of
the Company's operations at the beginning of the quarter due to the
COVID-19 pandemic, a lower head grade and a second shipment of
low-silica concentrate. Following the successful commercial production
test last quarter, DR pellet producers and direct reduced iron ("DRI")
plant operators have accepted the Company's product specifications which
confirms Bloom Lake's ability to produce DR quality iron ore
concentrate. With this confirmed product specification, the Company
produced an additional 207,900 wmt of DR quality iron ore concentrate at
67.8% Fe with a combined silica and alumina content of 2.68%, at the
request of a customer in the Middle East. This specific production of
low-silica concentrate reduced the quarterly recovery rate by 0.6%. This
second shipment confirms the ability of the Company to sell its ore to
producers of DR pellets, which can be converted by DRI producers and
utilized in electric arc furnaces, which represent a growing subset of
global steelmaking capacity. This positions the Company to potentially
increase its customers' base and confirms that Bloom Lake is one of the
few producing deposits globally that can transition its product offering
in response to potential shifts in steelmaking methods in the coming
years.
Based on the foregoing, Bloom
Lake produced 1,798,800 wmt of 66.5% Fe high-grade iron ore concentrate
during the three-month period ended June 30, 2020, a decrease of 10%,
compared to 1,989,400 wmt in the same period of the prior year. The
lower production is mainly a result of the Government mandated ramp down
of operations due to the COVID-19 pandemic, but still in line with the
plant's nameplate capacity.
The reduction of 8% in iron ore
concentrate sold during the three-month period ended June 30, 2020,
compared to the same period of the prior year, is a direct result of the
lower production associated with the Government mandated ramp down of
operations due to the COVID-19 pandemic, and this is partially offset by
the sale of the elevated iron ore inventory on hand at the end of March
2020.
Related
Link: Official
Document |