Performance
We incurred a gross loss in the third quarter from our steelmaking coal
business unit of $63 million compared with gross profit of $425 million
a year ago. Gross profit before depreciation and amortization in the
third quarter declined by $508 million from a year ago (see table
below), primarily due to a CAD$71 per tonne decrease in realized
steelmaking coal prices and a decline in sales volumes of 16%, or 1.0
million tonnes.
Our third quarter sales volumes of 5.1 million tonnes were within the
guidance range issued in the second quarter and slightly higher than the
second quarter of this year.
In the third quarter, we signed a non-binding term sheet reflecting an
agreement in principle with Westshore Terminals for the shipment of
steelmaking coal beyond the expiry of the current contract on March 31,
2021. The proposed agreement provides for the shipment of between 5 and
7 million tonnes annually at fixed loading charges and Teck will ship a
total of 32.25 million tonnes under the agreement over a period of
approximately five years. The proposed agreement with Westshore
Terminals complements upgrades at Neptune Bulk Terminals and capacity at
Ridley Terminals. Together, these will provide greater flexibility and
optionality for Teck shipments and contribute to reduced costs and
improved performance and reliability throughout our steelmaking coal
supply chain. The proposed agreement is subject to definitive
documentation and the financial terms of the agreement will not be made
public.
STEELMAKING COAL BUSINESS UNIT
(CAD$ in millions) |
Three months ended September 30, |
Nine months ended September 30, |
Year |
2020 |
2019 |
2020 |
2019 |
Steelmaking coal price (realized US$/tonne) |
$102 |
$156 |
$116 |
$175 |
Steelmaking coal price (realized CAD$/tonne) |
$135 |
$206 |
$157 |
$233 |
Production (million tonnes) |
5.1 |
6.5 |
15.1 |
19 |
Sales (million tonnes) |
5.1 |
6.1 |
15.8 |
18.7 |
Gross profit before depreciation and amortization |
$120 |
$628 |
$761 |
$2,456 |
Gross profit |
($63) |
$425 |
$241 |
$1,871 |
Property, plant and equipment expenditures |
$234 |
$184 |
$673 |
$481 |
Operations
As previously disclosed, we had planned mining and production outages at
our operations in the third quarter to correspond with anticipated
reduced demand related to COVID-19. In light of the above, we reduced
logistics capacity through the five-month planned shutdown at Neptune
Bulk Terminals, which was completed in September. As a result, our third
quarter production of 5.1 million tonnes was 22% lower than the same
period a year ago.
Despite the COVID-19 measures we have implemented, daily operating
productivities at our operations continue to achieve historical high
performance levels. Similar to the second quarter, the efficiencies
realized and supported by our RACE21™ innovation-driven business
transformation program resulted in a 5% improvement in third quarter
truck productivity, compared to the same period last year. The improved
productivities reduced material movement costs.
Outlook
We are expecting sales of 5.8 to 6.2 million tonnes in the fourth
quarter of 2020. Despite the reduced production in 2020, we continue to
maintain an annual production capacity of approximately 26 to 27 million
tonnes supported by the four operations in the Elk Valley.
We expect adjusted site cash cost of sales in the second half of 2020 to
be between $60 to $64 per tonne consistent with our previous guidance.
Higher costs of sales in the first and second quarters of 2020 were due
to logistics issues and the impacts of COVID-19 and are offset by our
cost reduction efforts and mine production curtailments through
temporary shutdowns in the second half of the year. Further, with the
closure of our Cardinal River Operations and the expansion of our
Elkview Operations completed in the first half of 2020, we have
structurally shifted the cost base lower for the business unit. RACE21™
continues to deliver value and with all of these factors combined, we
expect December adjusted site cash cost of sales to be below $60 per
tonne. While we are still refining our production plans and operating
cost estimates for 2021, we expect adjusted site cash cost of sales to
be in line with the second half of 2020 reflecting the structural shift
in the cost base.
Transportation costs in the second half of 2020 are expected to be
approximately $39 to $42 per tonne, consistent with our previously
issued guidance.
We expect sustaining capital expenditures for our steelmaking coal
operations to be approximately $620 million in 2020, including
approximately $285 million related to water treatment, $240 million for
ongoing operations and $95 million for sustaining capital projects
ongoing at Neptune Bulk Terminals. Included in the sustaining capital
expenditure guidance for 2020 is $140 million relating to increasing the
plant capacity at Elkview Operations and the development of new mining
areas at our Elk Valley Operations, including the Castle project at
Fording River Operations.
In addition to the 2020 capital expenditures noted
above, the Neptune Bulk Terminals facility upgrade
project includes $335
million to be spent in 2020 and approximately $210 million in 2021 and
is considered
growth capital. Compared to
our previous guidance, spending for 2020 has decreased slightly and
shifted
into 2021 due
to timing of project work and payments.
RACE21™ growth capital includes $25 million that will
be invested in the steelmaking coal operations,
relating to our autonomous
haulage pilot project at our Elkview Operations.
Capitalized stripping costs in 2020 are expected to
be approximately $310 to $340 million.
Related Link: Official
Document |