Quarterly
highlights
-
The Total
Recordable Injury Frequency Rate (TRIFR) improved to 2.1 at 30
September 2020 on a 12 month rolling basis, 13 per cent lower than
30 June 2020
-
Record
first quarter iron ore shipments of 44.3 million tonnes (mt) were
five per cent higher than Q1 FY20. Ore processed and railed also
achieved record Q1 performance
-
C1 costs
of US$12.74/wet metric tonne (wmt) in Q1 FY21 were two per cent
lower than the prior comparable period
-
Ongoing
demand for Fortescue’s products delivered average revenue of
US$106/dry metric tonne (dmt) in Q1 FY21, representing 89 per cent
of the average Platts 62% CFR Index
-
Strong
free cashflow generation in the quarter contributed to net cash of
US$1.0 billion at 30 September 2020, compared to net debt of US$0.3
billion at 30 June 2020
-
The
Eliwana Mine and Rail and Iron Bridge Magnetite projects remain on
schedule, with key milestones delivered for both projects in Q1 FY21
-
Approval
was received to increase the licensed throughput of the Herb Elliott
Port facility at Port Hedland from 175 million tonnes per annum
(mtpa) to 210mtpa on a staged basis
-
Guidance for FY21 shipments,
C1 costs and capital expenditure remains unchanged.
Fortescue
Chief Executive Officer, Elizabeth Gaines, said “Fortescue has delivered
a strong start to FY21 across all key measures of safety, production and
cost. The improvement in safety performance across the business was a
key highlight with a TRIFR of 2.1, down from 2.4 at 30 June 2020. At the
same time, a record result for first quarter shipments of 44.3mt was
achieved with lower C1 costs of US$12.74/wmt, reflecting our continued
focus on cost discipline.
“Robust
demand from our customers contributed to an increase in revenue
realisation, 31 per cent higher than the June Quarter and above the 27
per cent increase in the average Platts 62% CFR Index. We have
successfully grown and diversified our distribution channels, with
portside sales in China by FMG Trading Shanghai now exceeding 10mt since
sales commenced in June 2019.
“Our major
projects continue on schedule, including the commencement of pre-strip
mining and ore stockpiling at the Eliwana Mine and Rail project.
“Our COVID-19
risk management strategy and key measures remain in place to safeguard
our team and operations and we continue to generate a strong economic
contribution to the West Australian and national economy. We are
providing ongoing support to our East Coast team members who have been
impacted by the West Australian border closure and greatly appreciate
their ongoing commitment.”
“Against the
backdrop of a strong performance for the first quarter, we are well
positioned for FY21 to meet our guidance, execute our growth strategy
and deliver returns to our shareholders,” Ms Gaines said.
Operations
Production summary (m wmt) |
3Q2020 |
2Q2020 |
Var
(%) |
3Q2019 |
Var
(%) |
Ore
mined |
58.4 |
57.2 |
2 |
50.6 |
15 |
Overburden removed |
74.5 |
84.7 |
-12 |
86 |
-13 |
Ore
processed |
46 |
42.7 |
8 |
45.1 |
2 |
Ore
shipped |
44.3 |
47.3 |
-6 |
42.2 |
5 |
C1
cost (US$/wmt) |
12.74 |
13.02 |
-2 |
12.95 |
-2 |
Volume
references are based on wet metric tonnes (wmt). Product is shipped with
approximately 9 per cent moisture.
•
Fortescue’s 12 month rolling TRIFR was 2.1 at 30 September 2020,
representing a 13 per cent improvement from 2.4 at 30 June 2020 and the
injury severity rate continued its downward trend. An updated Job Hazard
Analysis program was implemented in September 2020, with strong
engagement across the operations and projects teams.
• A
comprehensive COVID-19 risk management strategy and key measures remain
in place to safeguard Fortescue team members and communities. There have
been no cases of COVID-19 across Fortescue’s operational sites.
• In a
strong start to FY21, mining, processing, rail and shipping combined to
deliver record first quarter iron ore shipments of 44.3mt, five per cent
higher than the prior comparable period and six per cent lower than Q4
FY20, reflecting planned seasonal maintenance activity. Ore processing
and rail achieved record first quarter volumes due to consistent
performance of the ore processing facilities and healthy product stocks
at mines.
• The Q1
FY21 strip ratio was 1.3 and is expected to average approximately 1.5 in
the current five year mine plan, excluding the Iron Bridge Magnetite
project.
• C1
costs of US$12.74/wmt in Q1 FY21 were two per cent lower than both the
prior comparable period and Q4 FY20 as the lower strip ratio and fuel
prices offset a stronger AUD:USD exchange rate.
• The
consolidation of the management of the Cloudbreak and Christmas Creek
mines into an integrated Chichester Hub has commenced. Following the
recent completion of the Chichester Hub’s autonomous haulage project,
this will further optimise productivity and efficiency by capturing
operational synergies.
Marketing
•
Chinese crude steel production reached 781.6mt in the nine months to
September 2020, increasing 4.5 per cent compared to the same period in
2019. Demand was very strong for sinter fines, supporting prices during
the quarter. Total iron ore stocks at Chinese ports rose from 108mt at
30 June 2020 to 116mt at 30 September 2020.
•
Average revenue for Q1 FY21 of US$105.77/dmt represented revenue
realisation of 89 per cent of the average Platts 62% CFR Index of
US$118.21/dmt. The Platts 62% CFR Index closed at US$123.15/dmt at 30
September 2020, compared to US$101.05/dmt at 30 June 2020.
•
Revenue per tonne increased by 31 per cent compared to Q4 FY20, higher
than the 27 per cent increase in the average Platts 62% CFR Index over
the same period reflecting robust demand for Fortescue’s products.
•
Fortescue’s wholly owned Chinese sales entity, FMG Trading Shanghai Co.
Ltd (FMG Trading) sold 2.8mt in Q1 FY21 from regional ports in China.
FMG Trading’s total portside sales has now exceeded 10mt.
Product summary (m wmt) |
Q1
FY21 |
(%) |
Q4
FY20 |
(%) |
Q1
FY20 |
(%) |
West
Pilbara Fines |
4.5 |
10 |
4.9 |
10 |
4.3 |
10 |
Kings
Fines |
3.7 |
8 |
4.2 |
9 |
3.4 |
8 |
Fortescue Blend |
17.7 |
40 |
17.1 |
36 |
18.1 |
43 |
Fortescue Lump |
3.9 |
9 |
4.1 |
9 |
2 |
5 |
Super
Special Fines |
14.3 |
32 |
16.8 |
36 |
14.4 |
34 |
Other
products |
0.2 |
0 |
0.2 |
0 |
0 |
0 |
Total
shipments |
44.3 |
100 |
47.3 |
100 |
42.2 |
100 |
Major
projects
Eliwana
• The
Eliwana Mine and Rail project achieved key milestones in the quarter
including commencement of pre-stripping and ore stockpiling, rail bridge
construction and the completion of structural and mechanical equipment
installation at the ore processing facility.
• The
construction workforce is currently at peak levels, with tracklaying
progressing and electrical and instrumentation installation well
advanced.
• The
forecast total investment for the Eliwana Mine and Rail project remains
US$1.325 - US$1.375 billion with first ore on train scheduled in
December 2020.
Iron Bridge
• The
Iron Bridge Magnetite project is progressing on schedule and budget,
with the first shipment of concentrate planned in the first half of
calendar year 2022.
• Key
milestones achieved in the quarter include over 80 per cent completion
of earthworks and first concrete poured for the ore processing facility.
•
Village installation and aerodrome construction is well advanced leading
into the main construction phase. Key process equipment manufacturing
and major module fabrication is progressing well.
• The
forecast total investment for the Iron Bridge Magnetite project is
US$2.6 billion. The project is an unincorporated joint venture between
FMG Magnetite Pty Ltd (69 per cent) and Formosa Steel IB Pty Ltd (31 per
cent), and Fortescue’s share of the total investment is US$2.1 billion.
Energy
• The
Chichester Solar Gas Hybrid project, owned and operated by Alinta
Energy, will provide a low emission energy solution, incorporating
large-scale solar to displace around 100 million litres annually of
diesel used in the existing Christmas Creek and Cloudbreak power
stations. Construction is advancing, and by the end of Q1 FY21
approximately 80,000 solar panels, 125 transmission towers and 45
kilometres of transmission line have been installed.
• The
US$700 million Pilbara Energy Connect project includes transmission
infrastructure, hybrid solar gas generation and large-scale battery
storage. The project will integrate Fortescue’s stationary energy
facilities in the Pilbara into an efficient network and will lower
emissions and the cost of electricity to existing and future sites. Bulk
earthworks are well advanced and 100 transmission poles have been
erected in preparation for transmission line installation.
Exploration
• Total
exploration and studies capital expenditure for Q1 FY21 was US$31
million.
• Iron
ore exploration in the Pilbara during the quarter focused on resource
definition drilling at Eliwana as well as other exploration programs in
the Western and Solomon Hubs.
• Early
stage exploration activities in the Paterson, Rudall and Goldfields
regions of Western Australia continued, along with drilling programs in
South Australia.
•
Exploration and field activities in Ecuador and Argentina remain
suspended due to COVID-19, with assessment of previous drilling results
and various geological studies continuing. Subject to COVID-19
restrictions, seasonal drilling activities in the San Juan region of
Argentina are expected to commence in Q2 FY21.
FY21
guidance
1.
Iron ore shipments of 175 - 180mt
2.
C1 costs of US$13.00 - US$13.50/wmt, based on
an assumed exchange rate of AUD:USD 0.70
3.
Capital expenditure of US$3.0 - US$3.4
billion, which is inclusive of:
a)
US$1.0 billion of sustaining, operational and
hub development capital
b)
US$140 million of exploration expenditure and
studies
c)
US$1.9 - US$2.3 billion for major projects
(Eliwana, Iron Bridge and Energy).
More Info:
FMG 3Q2020 Report |