Search: News Price
Home |  Register |  Price Index  |  Publication |  Consultancy |  Data |  Events |  Enquiry |  Language
Apr.24.2024 1USD=7.1048RMB
  SteelHome >>Raw Material>>Market Info>>Special Studies
 
Rio Tinto's 2Q2021 Pilbara Iron Ore Production Down 9% YoY to 75.9 Million Tonnes

https://en.steelhome.com [SteelHome] 2021-07-16 10:52:34

share to social network site

Rio Tinto posted 152.3 million tonnes of iron ore production in Pilbara in the first half of 2021, 5% lower than the first half of 2020 due to above average rainfall, shutdowns to enable replacement mines to be tied in, processing plant availability and cultural heritage management.

Second quarter production of 75.9 million tonnes (100% basis) was 9% lower than the second quarter of 2020. Its 2021 iron ore production guidance remains at 325 to 340 million tonnes in Pilbara.

Full Content by Rio Tinto

Pilbara operations

Pilbara operations produced 152.3 million tonnes (Rio Tinto share 126.9 million tonnes) in the first half of 2021, 5% lower than the first half of 2020 due to above average rainfall, shutdowns to enable replacement mines to be tied in, processing plant availability and cultural heritage management. Ongoing COVID-19 restrictions and a tight labour market have further impacted our ability to access experienced contractors and particular skill sets.

Sustained wet weather had an estimated impact of around 3 million tonnes in the first half. Consistent and above average rainfall impacted mine operations, particularly at West Pilbara and Robe Valley operations. The recorded rainfall days were 30% and 70% above the five year average at Paraburdoo and Karratha respectively, while rainfall at Pannawonica was 60% above the five year average.

The impact from shutdowns to enable replacement mines to be tied in at Western Turner Syncline and Robe Valley, and reduced processing plant availability, particularly at Yandicoogina, is estimated to be 4 million tonnes in the first half.

Execution of shutdowns was also impacted by labour shortages due to COVID-19 restrictions and high labour demand.

We continue to prioritise engagement with Traditional Owners and cultural heritage management in daily site operations. To date, 2021 production has been reduced by around 2 million tonnes as mine plans have been amended, and buffers and exclusion zones have been incorporated to protect areas of high cultural significance. Mine plan changes have also resulted in increased production of SP-10.

Blast management plans have been developed to create smaller, higher controlled blasts to minimise vibration and protect heritage sites (approximately 11% of blasts in the first half), which has had some impact on mining productivity and materials handling. Going forward this will remain a risk factor, however we are adapting mine practices and improving productivity.

Mine production risks remain in the second half, as we complete construction and commissioning of Gudai-Darri, our first new hub in over five years, and ramp up production from replacement mines. The increased tightness in Western Australia’s labour market continues, in particular shortages of roles relating to structural, mechanical, electrical and instrumentation disciplines, which is amplified by ongoing COVID-19 travel restrictions. Despite these impacts, all projects are expected to achieve first ore in the period previously disclosed, although completion in 2021 is slightly later than planned.

First half shipments of 154.1 million tonnes (Rio Tinto share 128.6 million tonnes) were 3% lower than the first half of 2020 with some additional drawdown of inventories. Full year iron ore shipments guidance is expected to be at the low end of the range and remains subject to COVID-19 disruptions, tie-in and ramp up of replacement mines and cultural heritage management.

In June we successfully completed a planned five week maintenance shut at one of our four port terminals, East Intercourse Island (EII), slightly ahead of plan. During the shut we replaced four ‘apron feeders’ below the rail car dumper that were around 50 years old.

Approximately 12% of sales in the first half were priced by reference to the prior quarter’s average index lagged by one month. The remainder was sold either on current quarter average, current month average or on the spot market.

Approximately 29% of sales in the first half were made on a free on board (FOB) basis, with the remainder sold including freight.

Achieved average pricing in the first half of 2021 was $154.9 per wet metric tonne on an FOB basis (equivalent to $168.4 per dry metric tonne, at 8% moisture assumption). This compares to the average first half price for the monthly average Platts index for 62% iron fines converted to an FOB basis of $172.6 per dry metric tonne.

On 22 June, we announced the deployment of the world’s first fully autonomous water trucks at Gudai-Darri. The three new water trucks will join a fleet of Caterpillar heavy mobile equipment including autonomous haul trucks and production drills, and will be primarily used for dust suppression on site. The trucks will enhance productivity by enabling mine operations to digitally track water consumption and reduce waste.

China Portside Trading

We continue to significantly increase port sales in China, with 5.4 million tonnes of sales in the first half of 2021 (3.6 million tonnes in the second quarter), doubling 2020’s volumes. In the second quarter, we surpassed 10 million tonnes since the programme commenced and completed the first bonded sale to a steel mill in Indonesia ex Zhanjiang port. Our portside operation handles product from our operations in the Pilbara and in Canada as well as third party product, and provides blending and screening capabilities. Approximately 85% of products sold were either blended or screened in Chinese ports in the first half of 2021.

Pilbara replacement projects

At Gudai-Darri, mining has commenced with more than nine million cubic metres of pre-stripping completed in June. Labour shortages have impacted both steel fabrication and site construction activities. First ore in the crusher is expected in 2021, although commissioning is later than originally planned. The project is expected to ramp up in early 2022, consistent with previous guidance.

First ore at West Angelas (C, D) was achieved in June with load commissioning expected later in the year following delays related to heritage management. First ore at Robe Valley (Mesa B, C, H) and Western Turner Syncline Phase 2 is still expected in 2021, consistent with previous guidance.

T1: Operational Data

 

Rio Tinto
interest

Q2
2020

Q3
2020

Q4
2020

Q1
2021

Q2
2021

H1
2020

H1
2021

Western Australia

 

 

 

 

 

 

 

 

Pilbara Operations

 

 

 

 

 

 

 

 

Saleable iron ore production ('000 tonnes)

 

 

 

 

 

 

 

Hamersley mines

   (a)

53,187

54,852

53,316

47,063

47,621

102,514

94,684

Hamersley - Channar (b)

100.0%

2,223

2,849

2,169

2,250

2,712

4,157

4,963

Hope Downs

50.0%

11,318

13,250

13,142

11,232

11,920

22,652

23,152

Robe River - Pannawonica (Mesas J and A)

53.0%

8,126

7,324

7,525

6,616

5,830

15,446

12,446

Robe River - West Angelas

53.0%

8,378

8,110

9,809

9,246

7,806

16,290

17,052

Total production ('000 tonnes)

 

83,232

86,385

85,961

76,406

75,889

161,059

152,296

Breakdown of total production:

 

 

 

 

 

 

 

 

Pilbara Blend and SP10 Lump (c)

 

23,222

22,674

25,888

21,901

21,946

45,813

43,847

Pilbara Blend and SP10 Fines (c)

 

37,100

40,725

38,316

34,356

34,743

70,906

69,099

Robe Valley Lump

 

2,502

2,639

2,574

2,467

2,300

5,279

4,767

Robe Valley Fines

 

5,625

4,685

4,951

4,149

3,530

10,167

7,679

Yandicoogina Fines (HIY)

 

14,784

15,662

14,233

13,534

13,369

28,893

26,903

Breakdown of total shipments:

 

 

 

 

 

 

 

 

Pilbara Blend Lump

 

20,339

19,118

20,155

15,740

15,631

37,844

31,371

Pilbara Blend Fines

 

40,379

39,230

42,727

35,777

34,607

73,576

70,384

Robe Valley Lump

 

2,110

2,098

2,351

1,934

1,762

4,245

3,696

Robe Valley Fines

 

5,659

5,140

5,778

4,532

4,131

10,730

8,663

Yandicoogina Fines (HIY)

 

15,578

14,203

15,055

14,222

13,640

28,491

27,862

SP10 Lump (c)

 

1,014

822

1,037

2,664

3,748

2,020

6,411

SP10 Fines (c)

 

1,603

1,488

1,771

2,923

2,817

2,692

5,740

Total shipments ('000 tonnes) (d)

 

86,681

82,099

88,873

77,791

76,336

159,598

154,128

Iron Ore Company of Canada

58.7%

 

 

 

 

 

 

 

Newfoundland & Labrador and Quebec in Canada

 

 

 

 

 

 

 

Saleable iron ore production:

 

 

 

 

 

 

 

 

Concentrates ('000 tonnes)

 

2,593

1,768

2,208

1,484

1,965

4,165

3,449

Pellets ('000 tonnes)

 

2,112

2,217

2,457

2,510

2,669

4,899

5,178

IOC Total production ('000 tonnes)

 

4,704

3,985

4,666

3,993

4,634

9,064

8,627

Shipments:

 

 

 

 

 

 

 

 

Concentrates ('000 tonnes)

 

2,402

2,307

1,970

1,735

1,785

4,115

3,521

Pellets ('000 tonnes)

 

2,248

2,347

2,620

2,515

2,220

5,261

4,734

IOC Total Shipments ('000 tonnes) (d)

 

4,650

4,654

4,591

4,250

4,005

9,376

8,255

Global Iron Ore Totals

 

 

 

 

 

 

 

 

Iron Ore Production ('000 tonnes)

 

87,936

90,370

90,627

80,400

80,523

170,123

160,923

Iron Ore Shipments ('000 tonnes)

 

91,332

86,753

93,464

82,041

80,341

168,974

162,383

Iron Ore Sales ('000 tonnes) (e)

 

91,361

86,398

92,942

80,319

81,068

168,758

161,388

(a) Includes 100% of production from Paraburdoo, Mt Tom Price, Western Turner Syncline, Marandoo, Yandicoogina, Brockman, Nammuldi, Silvergrass and the Eastern Range mines. Whilst Rio Tinto owns 54% of the Eastern Range mine, under the terms of the joint venture agreement, Hamersley Iron manages the operation and is obliged to purchase all mine production from the joint venture and therefore all of the production is included in Rio Tinto's share of production.
(b) Rio Tinto’s ownership interest in Channar mine increased from 60% to 100%, following conclusion of its joint venture with Sinosteel Corporation upon reaching planned 290 million tonnes production on 22 October 2020. Historic data is unchanged.
(c) SP10 include other lower grade products.
(d) Shipments includes material shipped to our portside trading facility in China which may not be sold onwards in the same period.
(e) Include Pilbara and IOC sales adjusted for portside trading movements and third party volumes sold.

T2: Guidance

 

2020

H1 2021

2021

Actuals

Actuals

Pilbara iron ore (shipments, 100% basis) (Mt)

331

154

325 to 340

IOC iron ore pellets and concentrate (production, Rio Tinto share) (Mt)

10.4

5.1

10.5 to 12.0


(To contact the reporter on this story: cody.wang@steelhome.cn or 86-555-2238837 18725550282)
Related News
上海市通信管理局
沪B2-20040629
Copyright© 2004-. SteelHome.com. All Rights Reserved
Shanghai SteelHome Information Technology Co., Ltd    Tel: +86) 021-50585733, 50585358    Fax: 021-50585277