Rio Tinto posted
152.3 million tonnes of iron ore production in Pilbara in the first half
of 2021,
5% lower than the first half of 2020 due to above average rainfall,
shutdowns to enable replacement mines to be tied in, processing plant
availability and cultural heritage management.
Second quarter production of 75.9 million tonnes (100% basis) was 9%
lower than the second quarter of 2020. Its 2021 iron ore production guidance remains at 325 to 340
million tonnes in Pilbara.
Full Content by Rio Tinto
Pilbara
operations
Pilbara
operations produced 152.3 million tonnes (Rio Tinto share 126.9 million
tonnes) in the first half of 2021, 5% lower than the first half of 2020
due to above average rainfall, shutdowns to enable replacement mines to
be tied in, processing plant availability and cultural heritage
management. Ongoing COVID-19 restrictions and a tight labour market have
further impacted our ability to access experienced contractors and
particular skill sets.
Sustained wet weather had an estimated impact of around 3 million tonnes
in the first half. Consistent and above average rainfall impacted mine
operations, particularly at West Pilbara and Robe Valley operations. The
recorded rainfall days were 30% and 70% above the five year average at
Paraburdoo and Karratha respectively, while rainfall at Pannawonica was
60% above the five year average.
The
impact from shutdowns to enable replacement mines to be tied in at
Western Turner Syncline and Robe Valley, and reduced processing plant
availability, particularly at Yandicoogina, is estimated to be 4 million
tonnes in the first half.
Execution of shutdowns was also impacted by labour shortages due to
COVID-19 restrictions and high labour demand.
We
continue to prioritise engagement with Traditional Owners and cultural
heritage management in daily site operations. To date, 2021 production
has been reduced by around 2 million tonnes as mine plans have been
amended, and buffers and exclusion zones have been incorporated to
protect areas of high cultural significance. Mine plan changes have also
resulted in increased production of SP-10.
Blast
management plans have been developed to create smaller, higher
controlled blasts to minimise vibration and protect heritage sites
(approximately 11% of blasts in the first half), which has had some
impact on mining productivity and materials handling. Going forward this
will remain a risk factor, however we are adapting mine practices and
improving productivity.
Mine
production risks remain in the second half, as we complete construction
and commissioning of Gudai-Darri, our first new hub in over five years,
and ramp up production from replacement mines. The increased tightness
in Western Australia’s labour market continues, in particular shortages
of roles relating to structural, mechanical, electrical and
instrumentation disciplines, which is amplified by ongoing COVID-19
travel restrictions. Despite these impacts, all projects are expected to
achieve first ore in the period previously disclosed, although
completion in 2021 is slightly later than planned.
First
half shipments of 154.1 million tonnes (Rio Tinto share 128.6 million
tonnes) were 3% lower than the first half of 2020 with some additional
drawdown of inventories. Full year iron ore shipments guidance is
expected to be at the low end of the range and remains subject to
COVID-19 disruptions, tie-in and ramp up of replacement mines and
cultural heritage management.
In June
we successfully completed a planned five week maintenance shut at one of
our four port terminals, East Intercourse Island (EII), slightly ahead
of plan. During the shut we replaced four ‘apron feeders’ below the rail
car dumper that were around 50 years old.
Approximately 12% of sales in the first half were priced by reference to
the prior quarter’s average index lagged by one month. The remainder was
sold either on current quarter average, current month average or on the
spot market.
Approximately 29% of sales in the first half were made on a free on
board (FOB) basis, with the remainder sold including freight.
Achieved average pricing in the first half of 2021 was $154.9 per wet
metric tonne on an FOB basis (equivalent to $168.4 per dry metric tonne,
at 8% moisture assumption). This compares to the average first half
price for the monthly average Platts index for 62% iron fines converted
to an FOB basis of $172.6 per dry metric tonne.
On 22
June, we announced the deployment of the world’s first fully autonomous
water trucks at Gudai-Darri. The three new water trucks will join a
fleet of Caterpillar heavy mobile equipment including autonomous haul
trucks and production drills, and will be primarily used for dust
suppression on site. The trucks will enhance productivity by enabling
mine operations to digitally track water consumption and reduce waste.
China
Portside Trading
We
continue to significantly increase port sales in China, with 5.4 million
tonnes of sales in the first half of 2021 (3.6 million tonnes in the
second quarter), doubling 2020’s volumes. In the second quarter, we
surpassed 10 million tonnes since the programme commenced and completed
the first bonded sale to a steel mill in Indonesia ex Zhanjiang port.
Our portside operation handles product from our operations in the
Pilbara and in Canada as well as third party product, and provides
blending and screening capabilities. Approximately 85% of products sold
were either blended or screened in Chinese ports in the first half of
2021.
Pilbara
replacement projects
At
Gudai-Darri, mining has commenced with more than nine million cubic
metres of pre-stripping completed in June. Labour shortages have
impacted both steel fabrication and site construction activities. First
ore in the crusher is expected in 2021, although commissioning is later
than originally planned. The project is expected to ramp up in early
2022, consistent with previous guidance.
First
ore at West Angelas (C, D) was achieved in June with load commissioning
expected later in the year following delays related to heritage
management. First ore at Robe Valley (Mesa B, C, H) and Western Turner
Syncline Phase 2 is still expected in 2021, consistent with previous
guidance.
T1: Operational Data
|
Rio Tinto
interest |
Q2
2020 |
Q3
2020 |
Q4
2020 |
Q1
2021 |
Q2
2021 |
H1
2020 |
H1
2021 |
Western Australia |
|
|
|
|
|
|
|
|
Pilbara Operations |
|
|
|
|
|
|
|
|
Saleable iron ore production ('000 tonnes) |
|
|
|
|
|
|
|
Hamersley mines |
(a) |
53,187 |
54,852 |
53,316 |
47,063 |
47,621 |
102,514 |
94,684 |
Hamersley - Channar (b) |
100.0% |
2,223 |
2,849 |
2,169 |
2,250 |
2,712 |
4,157 |
4,963 |
Hope Downs |
50.0% |
11,318 |
13,250 |
13,142 |
11,232 |
11,920 |
22,652 |
23,152 |
Robe River - Pannawonica (Mesas J and A) |
53.0% |
8,126 |
7,324 |
7,525 |
6,616 |
5,830 |
15,446 |
12,446 |
Robe River - West Angelas |
53.0% |
8,378 |
8,110 |
9,809 |
9,246 |
7,806 |
16,290 |
17,052 |
Total production ('000 tonnes) |
|
83,232 |
86,385 |
85,961 |
76,406 |
75,889 |
161,059 |
152,296 |
Breakdown of total production: |
|
|
|
|
|
|
|
|
Pilbara Blend and SP10 Lump (c) |
|
23,222 |
22,674 |
25,888 |
21,901 |
21,946 |
45,813 |
43,847 |
Pilbara Blend and SP10 Fines (c) |
|
37,100 |
40,725 |
38,316 |
34,356 |
34,743 |
70,906 |
69,099 |
Robe Valley Lump |
|
2,502 |
2,639 |
2,574 |
2,467 |
2,300 |
5,279 |
4,767 |
Robe Valley Fines |
|
5,625 |
4,685 |
4,951 |
4,149 |
3,530 |
10,167 |
7,679 |
Yandicoogina Fines (HIY) |
|
14,784 |
15,662 |
14,233 |
13,534 |
13,369 |
28,893 |
26,903 |
Breakdown of total shipments: |
|
|
|
|
|
|
|
|
Pilbara Blend Lump |
|
20,339 |
19,118 |
20,155 |
15,740 |
15,631 |
37,844 |
31,371 |
Pilbara Blend Fines |
|
40,379 |
39,230 |
42,727 |
35,777 |
34,607 |
73,576 |
70,384 |
Robe Valley Lump |
|
2,110 |
2,098 |
2,351 |
1,934 |
1,762 |
4,245 |
3,696 |
Robe Valley Fines |
|
5,659 |
5,140 |
5,778 |
4,532 |
4,131 |
10,730 |
8,663 |
Yandicoogina Fines (HIY) |
|
15,578 |
14,203 |
15,055 |
14,222 |
13,640 |
28,491 |
27,862 |
SP10 Lump (c) |
|
1,014 |
822 |
1,037 |
2,664 |
3,748 |
2,020 |
6,411 |
SP10 Fines (c) |
|
1,603 |
1,488 |
1,771 |
2,923 |
2,817 |
2,692 |
5,740 |
Total shipments ('000 tonnes) (d) |
|
86,681 |
82,099 |
88,873 |
77,791 |
76,336 |
159,598 |
154,128 |
Iron Ore Company of Canada |
58.7% |
|
|
|
|
|
|
|
Newfoundland & Labrador and Quebec in Canada |
|
|
|
|
|
|
|
Saleable iron ore production: |
|
|
|
|
|
|
|
|
Concentrates ('000 tonnes) |
|
2,593 |
1,768 |
2,208 |
1,484 |
1,965 |
4,165 |
3,449 |
Pellets ('000 tonnes) |
|
2,112 |
2,217 |
2,457 |
2,510 |
2,669 |
4,899 |
5,178 |
IOC Total production ('000 tonnes) |
|
4,704 |
3,985 |
4,666 |
3,993 |
4,634 |
9,064 |
8,627 |
Shipments: |
|
|
|
|
|
|
|
|
Concentrates ('000 tonnes) |
|
2,402 |
2,307 |
1,970 |
1,735 |
1,785 |
4,115 |
3,521 |
Pellets ('000 tonnes) |
|
2,248 |
2,347 |
2,620 |
2,515 |
2,220 |
5,261 |
4,734 |
IOC Total Shipments ('000 tonnes) (d) |
|
4,650 |
4,654 |
4,591 |
4,250 |
4,005 |
9,376 |
8,255 |
Global Iron Ore Totals |
|
|
|
|
|
|
|
|
Iron Ore Production ('000 tonnes) |
|
87,936 |
90,370 |
90,627 |
80,400 |
80,523 |
170,123 |
160,923 |
Iron Ore Shipments ('000 tonnes) |
|
91,332 |
86,753 |
93,464 |
82,041 |
80,341 |
168,974 |
162,383 |
Iron Ore Sales ('000 tonnes) (e) |
|
91,361 |
86,398 |
92,942 |
80,319 |
81,068 |
168,758 |
161,388 |
(a) Includes 100% of production from Paraburdoo, Mt Tom Price,
Western Turner Syncline, Marandoo, Yandicoogina, Brockman,
Nammuldi, Silvergrass and the Eastern Range mines. Whilst Rio
Tinto owns 54% of the Eastern Range mine, under the terms of the
joint venture agreement, Hamersley Iron manages the operation
and is obliged to purchase all mine production from the joint
venture and therefore all of the production is included in Rio
Tinto's share of production.
(b) Rio Tinto’s ownership interest in Channar mine increased
from 60% to 100%, following conclusion of its joint venture with
Sinosteel Corporation upon reaching planned 290 million tonnes
production on 22 October 2020. Historic data is unchanged.
(c) SP10 include other lower grade products.
(d) Shipments includes material shipped to our portside trading
facility in China which may not be sold onwards in the same
period.
(e) Include Pilbara and IOC sales adjusted for portside trading
movements and third party volumes sold. |
T2: Guidance
|
2020 |
H1 2021 |
2021 |
Actuals |
Actuals |
Pilbara iron ore (shipments, 100% basis) (Mt) |
331 |
154 |
325 to 340 |
IOC iron ore pellets and concentrate (production, Rio Tinto
share) (Mt) |
10.4 |
5.1 |
10.5 to 12.0 |
(To contact the reporter on this story: cody.wang@steelhome.cn or 86-555-2238837 18725550282) |